Sunday, April 19, 2009
School Renovations Update
You can see photos at the King School twitter: http://twitter.com/King_School
Wednesday, April 08, 2009
MLK School Renovations Update
Since then, quite a bit has happened at school in the way of renovations including:
- electrical upgrades;
- installation of a new security system;
- replacement of some classroom flooring in some rooms;
- updating of all bathrooms in the building;
- repaving of front drive;
- replacing the heating system;
- installation of wireless infrastructure;
- installation of new "white" boards in all classrooms.
During the upcoming spring break, we've got more work that will be completed including:
- replacement of more classroom flooring;
- installation of lockers in hallways;
- replace cabinetry and sinks in classrooms;
- painting doors and hallways.
WOW! It is going to be very exciting to come back from spring break to see the new improvements--especially the lockers! I know the kids are excited about the lockers!
Thursday, December 18, 2008
MLK Building Renovations Update
Some of the renovations have taken place already including installing the infrastructure for updated electrical service and wireless Internet. In addition, over the winter break, six classrooms will have new floors installed and corridor ceiling tiles will be replaced (which are original from 1969 I believe). I am hopeful that new carpet will be installed in the music room as well.
I continue to take suggestions for "wish list" items which may be purchased if there is"extra" bond money. Here is the complete "wish list" as of today:
- Resurface asphalt areas in front of school and parking lot
- Ident-A-Kid visitor check-in system technology package (computer, printer, webcam) – building techs do not support this direction.
- Ceiling mount existing projectors in art room, computer lab, in media center and in office conference room—NOT in music room
- Update signage around building - parking lot entrance?
- Signage at entrance of front drive making it clear where drop off occurs
- Interior signage
- Update cosmetics of parking lot entrance to make it look like an entrance (sign, planter)
- Can a schematic be provided?
- Is there a way to make it look more organic, less industrial
- New classroom furniture – tables, chairs
- Elmo projectors for all classrooms
- Sink in MP room for handwashing
- Smart/Active boards in each classrooom
- Replace hallway flooring, add pattern
- Replace flooring in classroom storage areas
- Carpet in the media center
- Carpet in teacher’s lounge
- Wireless or data jack in MP Room
- Ceiling tile replacement in media center.
- Upgrade sink and sink cabinet in the staff lounge
- Don’t replace white boards in rooms where they already exist
- Upgrade sink and sink cabinet in the staff lounge
- Interior signage
- Move classroom sinks closer to the middle of the counter space
- New toilet if office bathroom
- Update older drinking fountain across from office
- Cabinet in office for medication
- Stools for the computer lab
- spring/winter rodent problem
- install PA system in RI and resource room
- new door from gym to MP room
- Paint inside and outside of school
- Push-plate on entry door
- Handicapped push plate for main entrance door(s)
- Clean outlet pipe for catch basin in back playground
- Control over our own heat
- Bump out our cubbies to make our rooms larger and then doors leading from each classroom straight outside.
- Ceiling tiles in music room
- Remove old TV in music room
Wednesday, October 15, 2008
MLK Renovations Update
We will have a surplus (money projected to be left over after the bond is fulfilled) of $171,000. This money can be used to fund "wish list" items which were generated last year as part of the planning process. In no particular order, the "wish list" items show below.
One thing will be at the top of the wish list: asphalt. While I think everyone on the planning team thought it was clear we wanted the front drive to be resurfaced, this was not included in the projections last night. This means that a chunk of the surplus will go towards asphalt. This is only alarming in that I was expecting it to be included already. I've been reassured that it won't be a problem going forward.
If you think there is something to be added to the list below, please let me know and I'll add it so it can be considered.
- Resurface asphalt areas in front of school and parking lot
- Ident-A-Kid visitor check-in system technology package (computer, printer, webcam)
- Ceiling mount existing projectors in art room, music room, computer
lab, in media center and in office conference room - Update signage around building
- Update cosmetics of parking lot entrance to make it look like an entrance (sign, planter)
- New classroom furniture – tables, chairs
- Elmo document projectors for all classrooms
- Smart/Active boards for all classrooms
- Replace hallway flooring, add pattern
- Replace flooring in classroom storage areas
- Carpet in the media center
- Carpet in teacher's lounge
- Ceiling tile replacement in media center.
- Upgrade sink and sink cabinet in the staff lounge
- Move classroom sinks closer to the center of the counter space
- New toilet in office bathroom
- Update older drinking fountain across from office
- Cabinet in office for medication
Not all of what shows on the list will necessarily be purchased. At this point we are brainstorming.
Sincerely,
Kevin
Tuesday, October 07, 2008
MLK Building Renovations Presentation @ 10/14 PTO Meeting
Some of the highlights of the renovations to take place primarily in the summer of 2010 include:
- electrical upgrades
- installation of a new security system
- replacement of classroom flooring
- updating of all bathrooms in the building
- installation of lockers in hallways
- replace cabinetry and sinks in classrooms
- repaving of front drive
- replacing the heating system
- installation of wireless infrastructure
Wednesday, April 30, 2008
Front Drive Redesign - Input Sought - 5/7 @ 7 PM
The redesign of the front drive is intended to better ensure student safety during the busiest times of the day. The plan includes:
• A separate drop-off/pick-up lane for parents for use in the AM/PM;
• An “island” where students will transition to/from cars;
• A metal (but not chainlnk) fence on the “island” that will block students from crossing into the bus lane anywhere except at the crossing area directly in line with the front doors of the school;
• Increasing the width of the circle drive as much as 25 feet;
• Using grassy area in front of the school for the new drop-off/pick-up lane and the “island.”
King's Building Renovation Team has been meeting since September 2007 to consider and review improvements needed at King. The team includes representatives from the PTO, School Improvement Team and King faculty as well as experts from the district including architects, building planning personnel, traffic engineers, and facilities personnel.
In December 2007 the team sought input from the MLK community about the renovations. Now we are seeking input again--specifically on the front drive redesign—for consideration by the team. A meeting to share the plans and gather additional input will be held on May 7 at 7 PM at King School. Anyone who would like to give input is encouraged to attend.
To assist us in planning for the May 7 meeting, please RSVP by calling 994-1940 by May 7 at 9 AM or by sending an email to karrk@aaps.k12.mi.us. If you cannot attend but would like to give input via email, that can also be sent to karrk@aaps.k12.mi.us.
Graphic of Front Drive Redesign Proposal
Note: If you click on the image below, it will enlarge.