- electrical upgrades
- installation of a new security system
- replacement of classroom flooring
- updating of all bathrooms in the building
- installation of lockers in hallways
- replace cabinetry and sinks in classrooms
- reconfigure drop off area in front of school to better insure safety of students
- replace heating system
- install wireless infrastructure
The exciting part: Conceptual Drawings! At this point, I have conceptual drawings from the architects of what would be done at MLK . . . so . . . it is time to share the concepts and offer any final input on the concepts. With this goal in mind, I've left the drawings and the design specifications in the school office conference room. Please feel free to look them over. In addition, I will be available to share them on Thursday, December 20 from 11:30 to 1 and on Friday, December 21 from 9 to 10. I hope to see you at one of the meetings.